Approved a $1,070,286.13 contract with Ranger Construction Industries, Inc. to rebuild Britt Road and replace its culverts.

Approved Vote 5-0 $1,070,286.13 Roads and transportation

The vote: 5-0

Voted yes: Leslie Campione, Sean M. Parks, Anthony Sabatini, Kirby Smith, Timothy Morris

Motion by Anthony Sabatini, seconded by Timothy Morris. From the Clerk's official minutes.

Watch this part of the meeting (starts at 0:22:31)

Voted on as part of the consent agendaA group of routine items the Board votes on together with one motion. Any commissioner can pull an item out to discuss and vote on it separately. County Commission agendas (CivicClerk portal); the recording starts at that vote. The county's own recording.

In plain words

A contract to rebuild about 260 feet of Britt Road and replace its culverts after Hurricane Milton washed out the section.

What changes The county will award the construction contract to Ranger Construction Industries, Inc. and begin rebuilding the road and installing new culverts.

Who and the money The project costs $1,070,286.13, funded by $744,224.87 in grant money and $326,061.26 in ARPA funds, within the Fiscal Year 2026 Budget.

Stated reason (staff, quoted): "The project will address the section of Britt Road that washed out during Hurricane Milton and will include grading upstream and downstream of the road crossing."

Where Britt Road

Why (staff, quoted) "The project will address the section of Britt Road that washed out during Hurricane Milton and will include grading upstream and downstream of the road crossing."

Paid from ARPA

Backup in the packet: LAP Agreement (p. 165), Bid Comparison (p. 165), Other Bidders (p. 165)

Written from the Board ActionThe Clerk's same-week record of what the County Commission decided on each agenda tab. Vote tallies and discussion come later in the Board Minutes. Clerk of Court, Board Action and Board Minutes on Municode and the staff cover sheet, checked by script: every number appears in the record. Staff memo

From the record

Request from Public Works to recommend approval to award the Britt Road Reconstruction and Culvert Replacement construction project (Contract 26-711) to Ranger Construction Industries, Inc. for $1,070,286.13. The fiscal impact is $1,070,286.13 — $744,224.87 (revenue/expenditure - grant funded) and $326,061.26 (expenditure - ARPA), and is within, and will not exceed, the Fiscal Year 2026 Budget. Commission District 4.
Clerk of Court, Board Action, Jul 14, 2026, page 4. Open the official document
The Board approved the Consent Agenda, Tabs 3 through 14, pulling Tabs 11 and 13 to the regular agenda, as follows: PROCLAMATIONS Recommend approval of Croqueta Day Proclamation 2026-77, per Commissioner Sean Parks, by a vote of 5-0.
Clerk of Court, Board Minutes, Jul 14, 2026. Open the official document

The rest of this meeting

More on roads and transportation

↑